The ParnaĆba V is a 386MW natural gas-based thermoelectric power project under construction in the MaranhĆ£o state of Brazil.
Brazilian integrated energy company Eneva is developing the project with an estimated investment of approximately £222m ($290m).
The construction works on the project were started in the first half of 2019 with the start of commercial operations expected in 2022.
The ParnaĆba V power block is designed to utilise the heat produced during the electricity generation process at the ParnaĆba I power plant for steam-based power generation, hence doesnāt require additional natural gas.
Location and site details
The ParnaĆba V Ā thermoelectric power project is located in the municipality of Santo AntĆ“nio dos Lopes, in the Brazillian state of MaranhĆ£o.
The project site lies within the existing ParnaĆba I power complex, approximately 290km away from the port of Itaqui.
ParnaĆba V thermoelectric power project make-up
The ParnaĆba V combined cycle power project will be equipped with a 386MW STF-D600 steam turbine from GE, along with four heat recovery boilers, a condenser, and valves.
The project also involves the construction of a cooling tower and a water treatment plant with a capacity of 2,100m3 per hour.
Construction equipment
The construction of the ParnaĆba V power project involves the deployment of two 220 tonnes (t) cranes, and a strand jacks lifting system for lifting and installation operations.
Gas supply
The ParnaĆba power complex is supplied with natural gas by Enevaās subsidiary ParnaĆba Natural Gas, which currently produces approximately 8.4 million cubic metres (mcm) of natural gas a day from the ParnaĆba Basin.
Power evacuation
The electricity generated by the ParnaĆba V thermoelectric power plant will be evacuated and distributed through a 500kV substation at the site.
Contractors involved
Techint Engineering and Construction was awarded an engineering, procurement, and construction (EPC) turnkey contract 2019 for the development of the ParnaĆba V thermoelectric power project in February.
The scope of the contract includes the construction and assembly works of the ParnaĆba V facility as well as the conversion of the ParnaĆba I power plant into a closed-cycle operation.
General Electric (GE) received a contract worth approximately £80m ($100m) for the supply of turbo-generators equipment for the project.
Flenco Fluid System has been subcontracted by GE Global Parts & Products for the supply of auxiliary systems.
Jema Energy Group, in early 2020, was contracted for the supply and commissioning of critical power systems, including two 2150A rectifier sets and two sets of 100kVA inverters and bypasses.
Forship Engenharia was contracted in 2019 to provide its HMSWeb IT solution for the handover management system (HMSWeb) covering the complete management for quality, construction, assembly, mechanical completion, and commissioning of the project.
Cometto SPMT was contracted to provide loading, road transportation, internal handling, lifting, and positioning services for equipment installation, while Raccordi Forgiati supplied alloy steel outlet fittings for the project in 2020.
ParnaĆba V thermoelectric power project background
Eneva won the award for the ParnaĆba V power project in the energy auction held by the Brazilian Electrical Energy Agency (ANEEL) in August 2018.
ParnaĆba power complex
The ParnaĆba power complex comprises the 676MW ParnaĆba I t, the 519MW ParnaĆba II, the 178MW ParnaĆba III and the 56MW ParnaĆba IV operating gas-fired power plants, while the ParnaĆba V and the 92MW ParnaĆba VI power plants are under construction.